According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
C) Before work to start the project commences
A) After the executive has been appointed
B) When authorized by the corporate, programme management or the customer
D) When an organization produces its business plans

PeopleCert PRINCE2-Foundation Exam - Topic 3 Question 124 Discussion

Actual exam question for PeopleCert's PRINCE2-Foundation exam
Question #: 124
Topic #: 3
[All PRINCE2-Foundation Questions]

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to the 'continued business justification' principle in PRINCE2, a justifiable reason for a project is required before any work to start the project begins. This ensures that projects are initiated only when there is a clear business need, aligned with organizational objectives, and there is an expectation of value creation. The business case is developed during the initial stages of the project and is maintained and reviewed throughout the project lifecycle.