PRINCE2-Foundation Exam - Topic 3 Question 126 Discussion

Posted by Lavelle on Sep 29, 2026 at 03:25 AM

Which role represents the stakeholders who will operate the project's products after the project is complete?

Suggested Answer: B

In PRINCE2, the Senior User role represents the interests of those who will use the project's products, those for whom the products will enable benefits after the project is complete, and any others who might be affected by the project outputs. This role is essential in ensuring that the project delivers products that meet the users' needs and achieve the desired benefits for the organization. Reference: PRINCE2 7 Foundation Handbook and official training materials.


Get Premium PRINCE2-Foundation Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
4 comments · newest first
FA
Fatima 23 hours ago
I recall a similar question where the focus was on who benefits from the project outcome, and that pointed towards the senior user as well.
CH
Cherry 6 days ago
I feel like the executive role is more about decision-making, so it can't be A). I think it has to be B) Senior user, but I could be wrong.
LU
Luisa 11 days ago
I'm not entirely sure, but I remember a practice question where the project manager was more about overseeing the project rather than operating the product.
SA
Sabrina 16 days ago
I think the answer might be B) Senior user, since they represent the end users who will actually use the product.