Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 12 Question 105 Discussion

A team manager forecasts a work package will exceed time tolerance and raises an issue.Is this appropriate application of the progress practice, and why?
A) Yes, because forecast exceptions must be escalated
B) Yes, because planning should improve
C) No, because an exception report is required immediately
D) No, because escalation should wait

PRINCE2 Practitioner Exam - Topic 12 Question 105 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 105
Topic #: 12
[All PRINCE2 Practitioner Questions]

A team manager forecasts a work package will exceed time tolerance and raises an issue.

Is this appropriate application of the progress practice, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

PRINCE2 requires escalation when a tolerance is forecast to be exceeded, not after it is breached. Raising an issue is the correct first step.


Contribute your Thoughts:

0/2000 characters
Fannie
4 days ago
I think it's A. Escalating is crucial.
upvoted 0 times
...
Charlette
9 days ago
Not sure if escalation is always the right move, though...
upvoted 0 times
...
Micaela
14 days ago
Totally with you on A, better safe than sorry!
upvoted 0 times
...
Ashlee
19 days ago
Wait, why not just wait for an exception report? Seems odd.
upvoted 0 times
...
Annalee
25 days ago
I think B makes sense too, planning needs to get better.
upvoted 0 times
...
Delmy
30 days ago
Definitely A, gotta escalate those exceptions!
upvoted 0 times
...
Bulah
1 month ago
I’m not sure, is it really necessary to escalate right away?
upvoted 0 times
...
Ezekiel
1 month ago
Totally agree with A, better safe than sorry!
upvoted 0 times
...
Darell
2 months ago
Wait, why not just wait for an exception report? Seems odd.
upvoted 0 times
...
Katie
2 months ago
I think B makes sense too, planning needs to get better.
upvoted 0 times
...
Gilma
2 months ago
Definitely A, gotta escalate those exceptions!
upvoted 0 times
...
Deandrea
2 months ago
I thought escalation should happen right away, but I also remember some cases where waiting was advised, so I'm confused about option D.
upvoted 0 times
...
Novella
2 months ago
I feel like we discussed that an exception report is necessary when there's a significant issue, which might point to option C being correct.
upvoted 0 times
...
Francoise
2 months ago
I'm not entirely sure, but I remember something about planning needing to improve, so maybe option B could be valid too?
upvoted 0 times
...
Vicki
3 months ago
I think option A makes sense since we learned that any forecast exceptions should be escalated to keep everyone informed.
upvoted 0 times
...

Save Cancel