U.S. Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 12 Question 105 Discussion

A team manager forecasts a work package will exceed time tolerance and raises an issue.Is this appropriate application of the progress practice, and why?
A) Yes, because forecast exceptions must be escalated
B) Yes, because planning should improve
C) No, because an exception report is required immediately
D) No, because escalation should wait

PRINCE2 Practitioner Exam - Topic 12 Question 105 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 105
Topic #: 12
[All PRINCE2 Practitioner Questions]

A team manager forecasts a work package will exceed time tolerance and raises an issue.

Is this appropriate application of the progress practice, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

PRINCE2 requires escalation when a tolerance is forecast to be exceeded, not after it is breached. Raising an issue is the correct first step.


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel