How is Uncertainty Identified, assessed and controlled?
Suggested Answer: C
Get Premium PRINCE2-Foundation Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Uncertainty in a project is identified, assessed, and controlled by applying the risk practice. This practice involves systematic risk identification, analysis, and management, ensuring that risks are properly understood and addressed through appropriate responses to protect the project objectives. Reference: PRINCE2 Foundation official guide and risk management section.