Which of the following uses a flow-based approach to control work in progress?
Kanban uses a flow-based approach to visualize and control work in progress (WIP). It emphasizes limiting WIP to improve flow and reduce bottlenecks, with continuous monitoring via Kanban boards. This approach supports flexibility, transparency, and efficiency in managing tasks.
The Agilometer (A) measures agility, Lean (B) is a broad philosophy focusing on waste reduction, and Scrum (D) is an iterative framework but uses time-boxed sprints rather than flow-based control.