Which process monitors work that has been assigned to a team manager?
The 'Managing Product Delivery' process in PRINCE2 is designed to monitor the work assigned to a team manager. This process ensures that the work is completed according to the specifications agreed upon in the Work Package and provides a mechanism for the team manager to report progress back to the project manager. Reference: PRINCE2 Foundation Handbook, Managing Product Delivery section.