PRINCE2 Practitioner Exam - Topic 15 Question 100 Discussion
Which of the following is NOT an objective of Initiating a Project?
B) Understanding the roles and responsibilities of the Project Management Team
A) Understanding the scope of what is to be done and the products to be delivered
C) Understand how quality required will be achieved
D) Understand how progress will be monitored and controlled