PRINCE2-Foundation Exam - Topic 2 Question 121 Discussion

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
B) Manage by exception
A) Manage by stages
C) Continued business justification
D) Learn from experience

PRINCE2-Foundation Exam - Topic 2 Question 121 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 121
Topic #: 2
[All PRINCE2-Foundation Questions]

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Show Suggested Answer Hide Answer
Suggested Answer: B

The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is 'Manage by exception.' This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus. Reference: PRINCE2 Foundation manual, PRINCE2 official resources