PRINCE2 Practitioner Exam - Topic 2 Question 98 Discussion

Posted by Veronika on Mar 05, 2026 at 11:21 AM

The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.

Which 2 actions should the Team Manager take to check that the completed products have been approved as required?

Suggested Answer: B, D

Get Premium PRINCE2 Practitioner Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
31 comments · newest first
EL
Elsa 1 month ago
I feel the Configuration Management Strategy is less relevant here. Focus on approvals first.
SH
Shannon 2 months ago
Checking approval records is smart too. We need to confirm everything is documented.
CA
Carey 2 months ago
Agreed, but we should also look at the Product Descriptions. They outline approval responsibilities.
GE
Georgene 2 months ago
I think checking the Work Package is crucial. It shows who needs to approve.
MA
Magdalene 2 months ago
I feel C is relevant for procedures, but not as urgent as A and D.
TH
Thomasena 2 months ago
B could be useful too. Knowing who should approve helps.
FR
Francine 2 months ago
I agree, A is crucial. But D is also important for records.
LI
Linn 3 months ago
I think A and D are the best options. They directly address approval.
MA
Marnie 3 months ago
Yeah, we need to ensure everything is documented properly.
DW
Dwight 3 months ago
Definitely check the approval records too.
LO
Loreen 3 months ago
Agreed, but the Product Descriptions might also help.
TA
Tayna 3 months ago
I think checking the Work Package is crucial.
DE
Delfina 3 months ago
C seems less relevant, we need to focus on approvals first.
LI
Ligia 4 months ago
Totally agree with A, it's the first step to clear things up!
VA
Van 4 months ago
Wait, how did they finish without approvals? Sounds fishy.
SE
Selene 4 months ago
I think B is important too, can't skip on product descriptions.
DO
Dorothy 4 months ago
Definitely A and D, gotta verify those approvals!
WE
Wenona 4 months ago
C sounds useful too, but is it really necessary?
NO
Nobuko 5 months ago
Totally agree with A, that's the first thing to check!
LO
Louis 6 months ago
Wait, how can they finish without approval? Seems off.
VA
Valentine 6 months ago
I think B is also important, gotta know who should approve.
JE
Jestine 6 months ago
Definitely A and D, those are key steps!
ZE
Zena 7 months ago
What if the approval records are missing? That could be a problem.
CH
Chauncey 7 months ago
Totally agree with checking the Work Package first!
WI
Willetta 7 months ago
Wait, how did they finish without approval? Seems off.
AL
Alex 7 months ago
I think B is also important, can't overlook that.
MA
Maile 7 months ago
Definitely A and D, those are key steps!
RO
Rodolfo 7 months ago
The Configuration Management Strategy sounds relevant for handover procedures, but I’m not convinced it directly addresses the approval issue we have here.
AL
Aleta 8 months ago
I feel like checking the Product Descriptions could also be important, but I can't recall if it directly relates to the approval process.
LE
Leanora 8 months ago
I remember practicing a question like this, and I think checking the approval records in the Work Package is crucial to confirm everything is in order.
MA
Marget 8 months ago
I think we should definitely check the Work Package to see who was supposed to approve it, but I'm not entirely sure if that's the best first step.
0/2000 characters

Save Cancel