New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 2 Question 98 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 98
Topic #: 2
[All PRINCE2 Practitioner Questions]

The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.

Which 2 actions should the Team Manager take to check that the completed products have been approved as required?

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel