In which workshop are the project role descriptions created?
Suggested Answer: A
Get Premium PRINCE2-Agile-Foundation Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
The starting-up workshop is the initial workshop where the foundation for the project is established, including the creation and clarification of project role descriptions. Defining roles early ensures clarity of responsibilities, helps establish governance, and sets expectations for the project team.
Kickoff (B) focuses on launching the project, initiation (C) develops detailed plans, and the project canvas (D) is a tool for capturing high-level information but does not define roles explicitly.