Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Practitioner Exam - Topic 4 Question 101 Discussion

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?
C) Lessons Report
A) Issue Register
B) Follow-on action recommendations
D) Risk Register

PRINCE2 Practitioner Exam - Topic 4 Question 101 Discussion

Actual exam question for PRINCE2's PRINCE2 Practitioner exam
Question #: 101
Topic #: 4
[All PRINCE2 Practitioner Questions]

It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.

There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Elenor
4 days ago
Lessons Report could work too.
upvoted 0 times
...
Kayleigh
9 days ago
Good point!
upvoted 0 times
...
Leonora
14 days ago
Exactly, but it wasn't managed well.
upvoted 0 times
...
Charisse
19 days ago
But the risk was known early on!
upvoted 0 times
...
Leonora
25 days ago
I feel it's D) Risk Register.
upvoted 0 times
...
Helene
30 days ago
It tracks problems like this.
upvoted 0 times
...
Elenor
1 month ago
Why?
upvoted 0 times
...
Helene
1 month ago
I think it's A) Issue Register.
upvoted 0 times
...
Kayleigh
2 months ago
Tough question!
upvoted 0 times
...
Rolland
2 months ago
Issue Register makes sense too, but I lean towards Risk Register.
upvoted 0 times
...
Arthur
2 months ago
I think it’s obvious this was a major oversight.
upvoted 0 times
...
Kristofer
2 months ago
Wait, they’re closing the project? That’s surprising!
upvoted 0 times
...
Sharika
2 months ago
I disagree, it should go in the Lessons Report. We need to learn from this!
upvoted 0 times
...
Carissa
2 months ago
Definitely the Risk Register. That’s where risks should be tracked.
upvoted 0 times
...
Jill
3 months ago
I'm leaning towards the Risk Register because it seems to fit the scenario of a risk assessment being poor, but I wonder if the Issue Register could capture the immediate impact better.
upvoted 0 times
...
Alexis
4 months ago
I feel like the Lessons Report might be the right choice because it reflects on what went wrong, but I can't recall if it specifically covers risks identified earlier.
upvoted 0 times
...
Belen
4 months ago
I remember a practice question where we had to identify where to log risks, and I think the Issue Register could also be relevant here.
upvoted 0 times
...
Shizue
4 months ago
I think it might be the Risk Register since it tracks identified risks, but I'm not completely sure if it should be noted elsewhere too.
upvoted 0 times
...

Save Cancel