PRINCE2-Foundation Exam - Topic 1 Question 119 Discussion

In which step of the 'risk management technique should the organization's environment be considered?
A) Identify
B) Assess
C) Plan
D) Implement

PRINCE2-Foundation Exam - Topic 1 Question 119 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 119
Topic #: 1
[All PRINCE2-Foundation Questions]

In which step of the 'risk management technique should the organization's environment be considered?

Show Suggested Answer Hide Answer
Suggested Answer: A

Similar to question 397, the correct answer for considering the organization's environment in the risk management technique is during the 'Identify' step. This initial phase of risk management involves recognizing and recording risks after considering various environmental factors that can influence the project.

PRINCE2 7 Foundation guide on risk management.


Contribute your Thoughts:

0/2000 characters
Portia
4 days ago
C) Plan could work. Strategies depend on environment.
upvoted 0 times
...
Dulce
9 days ago
I agree, but B) Assess makes sense too. Need to evaluate surroundings.
upvoted 0 times
...
Afton
14 days ago
I think it's A) Identify. Environment impacts risks.
upvoted 0 times
...
Bo
19 days ago
A) Identify is key. Without knowing the environment, how can you assess?
upvoted 0 times
...
Carolynn
25 days ago
I lean towards B) Assess. It’s where you really evaluate risks.
upvoted 0 times
...
Angella
30 days ago
D) Implement is too late. Environment should be considered earlier.
upvoted 0 times
...
Alonzo
1 month ago
I feel like C) Plan is crucial. You need to adapt plans to the environment.
upvoted 0 times
...
Rene
1 month ago
I agree, but A) Identify makes sense too. You need to know the environment first.
upvoted 0 times
...
Ruthann
2 months ago
I think it's B) Assess. Environment impacts risk.
upvoted 0 times
...
Bernadine
2 months ago
Environment impacts all steps, but B is the most critical.
upvoted 0 times
...
Tyra
2 months ago
Wait, are we sure it's not C) Plan? That seems important too!
upvoted 0 times
...
Alva
2 months ago
I agree with B) Assess. Makes sense to evaluate the environment then.
upvoted 0 times
...
Jutta
2 months ago
I thought it was A) Identify. Isn't that where you look at the context?
upvoted 0 times
...
Lakeesha
2 months ago
It's definitely B) Assess. Environment plays a big role there.
upvoted 0 times
...
Sue
3 months ago
I'm leaning towards Assess as well, since that's when you evaluate the risks based on the environment, but I could be wrong.
upvoted 0 times
...
Virgina
4 months ago
I feel like it might be in the Plan step because that's where you strategize, but I could be mixing it up with another topic.
upvoted 0 times
...
Alline
4 months ago
I remember practicing a question similar to this, and I think it was about identifying risks in the Identify step.
upvoted 0 times
...
Herman
4 months ago
I think the organization's environment is considered in the Assess step, but I'm not entirely sure.
upvoted 0 times
...