From whom does a Team Manager obtain approval for a completed product?
In the PRINCE2 methodology, the Team Manager obtains approval for a completed product from the Project Manager. The Project Manager is responsible for ensuring that the products delivered by the Team Managers meet the project's standards and requirements before accepting them. Reference: PRINCE2 Foundation official documentation and study materials.