From whom does a Team Manager obtain approval for a completed product?
A) Project Manager
B) Project Support
C) The authority defined in the Product Description
D) Senior Supplier

PeopleCert PRINCE2-Foundation Exam - Topic 1 Question 125 Discussion

Actual exam question for PeopleCert's PRINCE2-Foundation exam
Question #: 125
Topic #: 1
[All PRINCE2-Foundation Questions]

From whom does a Team Manager obtain approval for a completed product?

Show Suggested Answer Hide Answer
Suggested Answer: A

In the PRINCE2 methodology, the Team Manager obtains approval for a completed product from the Project Manager. The Project Manager is responsible for ensuring that the products delivered by the Team Managers meet the project's standards and requirements before accepting them. Reference: PRINCE2 Foundation official documentation and study materials.