Which is consistent with the eight guidance points of PRINCE2 Agile?
B) The project manager role is NOT defined by Scrum or Kanban.
A) The project manager role is NOT required when incorporating IT-only frameworks.
C) Working in an agile way removes the need for a project manager.
D) A project manager is indicative of a 'command and control' culture.

PeopleCert PRINCE2 Agile Practitioner Exam - Topic 5 Question 30 Discussion

Actual exam question for PeopleCert's PRINCE2 Agile Practitioner exam
Question #: 30
Topic #: 5
[All PRINCE2 Agile Practitioner Questions]

Which is consistent with the eight guidance points of PRINCE2 Agile?

Show Suggested Answer Hide Answer
Suggested Answer: B

This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.