PeopleCert MSP Foundation Exam - Topic 1 Question 13 Discussion

Actual exam question for PeopleCert's MSP Foundation exam
Question #: 13
Topic #: 1
[All MSP Foundation Questions]

What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Erick
4 months ago
The Programme Office usually doesn't represent business interests directly.
upvoted 0 times
...
Bulah
4 months ago
Wait, are you all sure about that? Sounds off to me.
upvoted 0 times
...
Erick
4 months ago
Definitely the Programme Manager, they oversee everything!
upvoted 0 times
...
Dalene
4 months ago
I think the Programme Manager fits that role better.
upvoted 0 times
...
Roslyn
4 months ago
I'm pretty sure it's the Business Change Manager.
upvoted 0 times
...
Isabella
5 months ago
The Programme Board seems like a collective role, so I doubt it's the answer. I’m leaning towards the Programme Manager, but I could be wrong.
upvoted 0 times
...
Lajuana
5 months ago
I feel like the Programme Office could be involved, but they usually handle more administrative tasks, right?
upvoted 0 times
...
Hillary
5 months ago
I think the Business Change Manager might be the right choice since they focus on aligning projects with business needs, but I'm not entirely sure.
upvoted 0 times
...
Haydee
5 months ago
I remember practicing a question about roles in project management, and I think the Programme Manager often represents business interests too.
upvoted 0 times
...
Emelda
5 months ago
Hmm, I'm not totally sure about this one. I was thinking it might be C, to cover both expected and unexpected losses, but I'm not 100% confident. Gonna have to think this through a bit more.
upvoted 0 times
...
Lottie
5 months ago
I'm pretty sure the answer is B. Dev Hub. That's the key component for managing scratch orgs in SalesforceDX.
upvoted 0 times
...
Julene
5 months ago
I'm pretty sure the answer is D. Common Weaknesses Enumeration (CWE) is the standard list of software weaknesses.
upvoted 0 times
...
Paola
5 months ago
I think it's something about enabling it globally first, right? But I'm not entirely sure.
upvoted 0 times
...

Save Cancel