Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Scrum PSPO-I Exam - Topic 3 Question 47 Discussion

Actual exam question for Scrum's PSPO-I exam
Question #: 47
Topic #: 3
[All PSPO-I Questions]

What happens if the Scrum Team cannot complete its work by the end of the Sprint?

(choose the best answer)

Show Suggested Answer Hide Answer
Suggested Answer: A

If the Scrum Team cannot complete its work by the end of the Sprint, the Sprint does not get extended. Instead, the unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint12. This approach allows the team to get better at estimating and reduces complexity due to the consistency of the Scrum Events2. The Scrum Team continuously learns and adapts12.


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel