Which of the following steps in a business process can be the trigger for an update of the quality level? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, C, E

Contribute your Thoughts:

Larue
6 days ago
I'm not sure about C and D, but I think A and B make sense because they involve quality-related actions.
upvoted 0 times
...
Harris
7 days ago
I agree with Glynda, creating a quality notification and making the usage decision can trigger an update of the quality level.
upvoted 0 times
...
Glynda
9 days ago
I think it's A and B.
upvoted 0 times
...