Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are:
Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator ''Requirements immediately'' in customizing for your project profile.
When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator ''Requirements on release'' in customizing for your network type or activity type. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
Tayna
1 months agoLindsey
9 days agoCathern
1 months agoFrancine
1 months agoElise
1 months agoCorrinne
3 days agoRueben
4 days agoKenny
5 days agoTwana
6 days agoAleta
22 days agoWhitley
1 months agoElvera
2 months agoBarbra
21 days agoBeula
1 months agoRaylene
2 months agoMelissa
2 months agoJenifer
2 months agoFletcher
2 months agoAlaine
3 months ago