Which planning method can prevent further rescheduling of activities?
Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can still be rescheduled according to the project progress and resource availability. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are:
Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator ''Requirements immediately'' in customizing for your project profile.
When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator ''Requirements on release'' in customizing for your network type or activity type. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question
Goods receipt into unvaluated project stock and goods receipt of a non-stock item do not lead to the booking of actual costs to an object. Goods receipt into unvaluated project stock does not affect inventory valuation or accounting documents, therefore no actual costs are posted. Goods receipt of a non-stock item does not affect inventory valuation either, but only updates the purchase order history and statistical delivery costs, therefore no actual costs are posted. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
To set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing, you use the data entry profile as an influencing field. CATS is a tool that allows you to record working times and tasks for project activities. The data entry profile is a parameter that defines the layout and functions of the CATS user interface. You can use the data entry profile to determine which fields are displayed or hidden, mandatory or optional, modifiable or read-only, and so on. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
Betty Murphy
26 days agoGerald Collins
1 month agoSteven Lee
2 months agoRachel Evans
2 months agoSusan Ramirez
3 months agoBrenda Morris
3 months agoDennis Collins
4 months agoMichelle Nelson
4 months agoKevin Smith
5 months agoKaren Hill
5 months agoOlivia Rivera
5 months agoJohn Nguyen
5 months agoLaura Harris
5 months agoHarold Evans
5 months agoStephanie Lee
5 months agoHubert
8 months agoEnola
8 months agoYen
9 months agoHyman
9 months agoEdgar
9 months agoGalen
9 months agoRicki
10 months agoShawnee
10 months agoAlexia
10 months agoKasandra
10 months agoBrent
11 months agoDana
11 months agoKirby
11 months agoMendy
11 months agoElly
12 months agoTamra
12 months agoBlossom
1 year agoJeanice
1 year agoKristofer
1 year agoJolanda
1 year agoCyril
1 year agoDelisa
1 year agoTresa
2 years agoTamekia
2 years agoLemuel
2 years agoLaine
2 years agoLaticia
2 years agoViva
2 years agoLourdes
2 years agoFelix
2 years agoDella
2 years agoDonte
2 years agoShenika
2 years agoJosephine
2 years agoDavida
2 years agoProvidencia
2 years agoShawnee
2 years agoAugustine
2 years agoBeatriz
2 years agoCordie
2 years agoLeonida
2 years agoTish
2 years agoEva
2 years agoMari
2 years agoMarsha
2 years agoLizette
2 years agoNaomi
2 years agoSimona
2 years agoKatie
2 years agoLashawnda
2 years ago