Merlyn
2 months ago
Wait, is the answer 'All of the above'? Because that's the only way I'm getting this one right.
upvoted 0 times
...
Anika
3 months ago
This question is a piece of cake! The answer is clearly C) Project profile. It's like they're not even trying to trick us.
upvoted 0 times
...
Jerry
3 months ago
I bet the answer is A) Network profile. That's where all the magic happens, am I right?
upvoted 0 times
Shawnee
2 months ago
Actually, it is C) Project profile that influences the field selection in CATS. It's important to choose the right profile for your needs.
upvoted 0 times
...
Dean
2 months ago
I think it might be B) Data entry profile instead. That's what I usually use for field selection.
upvoted 0 times
...
Arlen
2 months ago
Yes, you are correct! A) Network profile is the influencing field for setting up the field selection in CATS.
upvoted 0 times
...
...
Ahmed
3 months ago
Hmm, I'm not sure, but I'm leaning towards D) Network type. Isn't that related to the CATS setup in some way?
upvoted 0 times
Marshall
29 days ago
Let's review the options again to make sure we select the correct influencing field.
upvoted 0 times
...
Bernadine
1 months ago
Maybe we should double check the documentation to be sure.
upvoted 0 times
...
Bernadine
1 months ago
I believe it's actually Data entry profile that is used for setting up the field selection.
upvoted 0 times
...
King
1 months ago
I think you might be right, Network type could be the influencing field.
upvoted 0 times
...
...
Lennie
3 months ago
B) Data entry profile sounds more like it to me. That's where you'd configure the fields for time sheet data entry.
upvoted 0 times
Jaclyn
2 months ago
I think it's important to customize the data entry profile to match the specific requirements of the project.
upvoted 0 times
...
Lauran
2 months ago
Yes, that's where you can define which fields are available for data entry in the time sheet.
upvoted 0 times
...
Theodora
2 months ago
I agree, B) Data entry profile is the correct option for setting up field selection in CATS.
upvoted 0 times
...
...
Iraida
4 months ago
I see your point, but I still think B) Data entry profile makes more sense because it directly influences field selection.
upvoted 0 times
...
Cyril
4 months ago
I think the answer is C) Project profile. That's where you set up the field selection for CATS, right?
upvoted 0 times
Daniel
3 months ago
No, the correct answer is B) Data entry profile. That is the influencing field used for setting up the field selection of CATS.
upvoted 0 times
...
Tegan
3 months ago
Yes, you are correct. The Project profile is used to set up the field selection for CATS.
upvoted 0 times
...
...
Keneth
4 months ago
I disagree, I believe the answer is C) Project profile.
upvoted 0 times
...
Iraida
4 months ago
I think the answer is B) Data entry profile.
upvoted 0 times
...