You are the project manager of the NNN Project. Stakeholders in the two-year project have
requested to send status reports to them via email every week. You have agreed and are sending the
reports on each Thursday. After six months of the project, the stakeholders are pleased with the
project progress and they would like you to reduce the status reports to every two weeks. What
process will examine the change to this project process and implement it in the project?
The project's Communications Management Plan defines what information will be distributed, when
it will be distributed, to whom it will be
distributed, and the modality of the information.
Answer option D is incorrect. The Schedule Management Plan defines the project work, when the
project work will happen, resource
utilization, and how the schedule will be monitored and controlled.
Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder
Management Plan.
Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be
created, how the changes will be allowed,
how the scope will be executed, monitored and controlled, and finally closed.
Emerson
9 days agoDusti
12 days agoJohanna
1 months agoFidelia
3 days agoAudry
11 days agoIvette
21 days agoEladia
1 months agoKendra
1 months agoAshton
1 months agoClaribel
9 days agoFrancine
10 days agoEmogene
13 days agoKattie
16 days agoElin
20 days agoAlyce
23 days agoMariko
2 months agoJeff
2 months agoNaomi
2 months agoGilma
2 months ago