Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Scheduling Professional Exam

Certification Provider: PMI
Exam Name: PMI Scheduling Professional
Duration: 120 Minutes
Number of questions in our database: 326
Exam Version: Apr. 06, 2024
Exam Official Topics:
  • Topic 1: Collect resource information and updates via reports, timesheets, meetings, inspections/ Develop the project resource breakdown structure (RBS)
  • Topic 2: Identify critical and near-critical path(s) using techniques such as Critical Path Method/ Establish scheduling policies and procedures regarding methodology
  • Topic 3: Define activities and milestones through communication with subject matter experts/ Develop the scheduling-related components for project management plans
  • Topic 4: Perform schedule analysis and audit, on in-house and subcontractor schedules/ Provide information about project scheduling objectives and goals
  • Topic 5: Establish project schedule configuration management policies and procedures incorporating best practices/ Align schedule with the overall program plan or integrated master plan (IMP)
  • Topic 6: Obtain a consensus of the project customer, sponsor, project manager/ Update the schedule model and document schedule baseline changes
  • Topic 7: Develop schedule approach, based on the unique characteristics of the project/ Incorporate approved risk mitigation activities into the schedule
  • Topic 8: Collect activity status at defined intervals from activity owners via reports, meetings, inspections/ Sequence activities, incorporating defined dependencies Perform schedule risk analysis using quantitative tools or techniques/ Analyze major milestones against statement of work (SOW)
  • Topic 9: Adjust schedule model based upon resource availability/ Establish the Performance Measurement Baseline (PMB)
Disscuss PMI PMI Scheduling Professional Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!

Free PMI PMI Scheduling Professional Exam Actual Questions

The questions for PMI Scheduling Professional were last updated On Apr. 06, 2024

Question #1

with the appropriate word. When activities are logically linked, they become the .

__________

Reveal Solution Hide Solution
Correct Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Question #2

A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.

Reveal Solution Hide Solution
Correct Answer: A, B, D

A scheduler schedules the constraints for the project into phases with respect to the

time and resources available. He can be hired from

outside a company, or from within a company. The basic roles of a scheduler are as follows:

Feasibility Planning: A scheduler is the time management expert who paints a picture of the project.

He develops a strategy for

delivery and to gain consensus.

Execution Schedule: A scheduler works with the project team to optimize and refine the schedule

until an agreed schedule has been

developed.

Performance Control: A schedule is maintained by the scheduler who optimizes outcomes and

instructs the project team on their

presentation. It is important that the scheduler be aware of the changes and trends related to the

project delivery.

Answer option C is incorrect. This is the skill possessed by the project manager.


Question #3

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Reveal Solution Hide Solution
Correct Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Question #4

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

Reveal Solution Hide Solution
Correct Answer: D

Stakeholders are interviewed and can help identify other stakeholders that should be

included in the project communications.

Answer option B is incorrect. According to the PMBOK, this is not the best answer.

Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by

it.

Answer option C is incorrect. Project customers are stakeholders.


Question #5

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Reveal Solution Hide Solution
Correct Answer: A


Unlock all PMI Scheduling Professional Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel