Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 70 Discussion

Actual exam question for PMI's PMI Scheduling Professional exam
Question #: 70
Topic #: 5
[All PMI Scheduling Professional Questions]

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Tiffiny
25 days ago
I don't know, guys. If the project schedule is fixed, then the delay might not impact the end date at all. Maybe the answer is A?
upvoted 0 times
...
Lamar
26 days ago
Okay, let's think this through. If Stephen is two days late on Activity B, that means the entire project will be delayed by two days, right? So, the answer must be C.
upvoted 0 times
...
Scarlet
27 days ago
Hmm, let's take a closer look at the diagram. Activity B is on the critical path, so any delay in that activity will directly affect the project end date.
upvoted 0 times
Phung
11 days ago
The project will be late by two days if Stephen is two days late.
upvoted 0 times
...
Darrel
12 days ago
Stephen's delay will impact the project end date.
upvoted 0 times
...
Andree
13 days ago
Activity B is on the critical path.
upvoted 0 times
...
...
Whitley
28 days ago
Ah, this is a tricky one! The project schedule is fixed, so we need to carefully analyze the impact of Stephen's delay on the critical path.
upvoted 0 times
...

Save Cancel