Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI-SP Exam - Topic 5 Question 113 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 113
Topic #: 5
[All PMI-SP Questions]

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Clorinda
8 days ago
I thought I recalled something about buffers in fixed schedules, but if there’s no buffer, then the lateness should directly affect the end date. I’m leaning towards C as well.
upvoted 0 times
...
Alishia
13 days ago
This seems similar to a practice question we did where a delay in a critical task pushed the end date. I feel like the answer is C, but I’m not 100% confident.
upvoted 0 times
...
Galen
18 days ago
I’m not entirely sure, but I think if Stephen is two days late and it’s on the critical path, the project could be late by those two days.
upvoted 0 times
...
Lou
23 days ago
I remember we discussed how fixed schedules can really complicate things. If Activity B is critical, then I think the project might be late.
upvoted 0 times
...

Save Cancel