Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 4 Question 113 Discussion

Actual exam question for PMI's PgMP exam
Question #: 113
Topic #: 4
[All PgMP Questions]

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively

address the risks.

In this situation, what should the program manager change about the risk management plan?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Nohemi
8 days ago
I vaguely recall that assigning resolution to the component project manager might not be enough if they’re already overwhelmed.
upvoted 0 times
...
Broderick
13 days ago
I feel like increasing flexibility could help, but I’m not clear on how that would actually work in practice.
upvoted 0 times
...
Hillary
18 days ago
I think we practiced a similar question where the focus was on escalation procedures. It makes sense to include those in the risk response plan.
upvoted 0 times
...
Corinne
23 days ago
I remember we discussed how important it is for the program manager to stay involved in risk management, but I'm not sure if delegating responsibilities is the best approach.
upvoted 0 times
...

Save Cancel