What is the architect's role in project closeout?
During project closeout, the architect conducts final inspections, prepares punch lists, and issues certificates of substantial completion to mark the transition of responsibility. Payroll and maintenance are owner or contractor roles. Warranty repairs may involve the architect as a liaison but are typically contractor responsibilities. ARE 5.0 PjM includes closeout procedures in the construction administration phase.