Microsoft Exam MB-240 Topic 1 Question 88 Discussion

Actual exam question for Microsoft's MB-240 exam
Question #: 88
Topic #: 1
[All MB-240 Questions]

You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days,

week, or months.

How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Thaddeus
6 days ago
I'm not sure, but I think C) Use Resource Crew Scheduling could also work for this scenario.
upvoted 0 times
...
Gracia
8 days ago
I agree, B is the correct answer. Multi-Resource Scheduling is the tool designed for this exact scenario.
upvoted 0 times
...
Cordie
12 days ago
Definitely B. Multi-Resource Scheduling is the feature you want to use when you need to schedule a team to work together for a specific duration.
upvoted 0 times
Aja
10 hours ago
B) Use Multi-Resource Scheduling
upvoted 0 times
...
...
Margart
22 days ago
I agree with Kassandra, using Multi-Resource Scheduling makes sense for scheduling a group of resources.
upvoted 0 times
...
Fernanda
25 days ago
B) Multi-Resource Scheduling seems like the way to go here. It's perfect for scheduling a group of resources to work together for a set time period.
upvoted 0 times
Louvenia
2 days ago
A) Use Facility Scheduling
upvoted 0 times
...
...
Kassandra
25 days ago
I think the answer is B) Use Multi-Resource Scheduling.
upvoted 0 times
...