Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam 70-348 Topic 14 Question 3 Discussion

Actual exam question for Microsoft's 70-348 exam
Question #: 3
Topic #: 14
[All 70-348 Questions]

You are a project manager in an organization that uses Microsoft PPM.

You have been given additional responsibilities managing existing projects created by another project manager.

When reviewing the project plan, you observe that some of the upcoming tasks are assigned to a generic resource.

You need to update the generic tasks to use defined resources.

Which type of resource should you use?

Show Suggested Answer Hide Answer
Suggested Answer: D

Comments

Currently there are no comments in this discussion, be the first to comment!


Save Cancel