ISTQB Exam ATM Topic 3 Question 35 Discussion

Actual exam question for ISTQB's ATM exam
Question #: 35
Topic #: 3
[All ATM Questions]

You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.

At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.

Which of the following statements is true in this context?

K4 3 credits

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sabine
26 days ago
Testing? More like 'guessing' in this project. I bet the developers are already working on features for the last six iterations, and the requirements are still 'drafty'.
upvoted 0 times
...
Anjelica
27 days ago
Option A is a trap. Freezing requirements completely before testing? That's just asking for trouble in an agile world.
upvoted 0 times
...
Nicolette
28 days ago
Haha, option D is a classic 'do the opposite of what you should' kind of answer. Sequential life cycle and iterative are like night and day when it comes to testing.
upvoted 0 times
Ettie
14 days ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
...
Vernice
29 days ago
I disagree with option C. Waiting until the last iteration to do all the system testing is a recipe for disaster in an iterative model.
upvoted 0 times
...
Ronald
1 months ago
Option B makes the most sense. With an iterative life cycle, system testing should be integrated throughout the development process, not just at the end.
upvoted 0 times
Xochitl
10 days ago
A) The system test phase should start when all the requirements are frozen
upvoted 0 times
...
Crista
1 months ago
B) You should allocate a large effort for system testing during the first three iterations
upvoted 0 times
...
...
Stevie
2 months ago
I believe the system test phase should start when all the requirements are frozen. It's crucial for overall quality.
upvoted 0 times
...
Sommer
2 months ago
I agree with Helene. It's important to ensure the core features are stable before adding additional features.
upvoted 0 times
...
Helene
2 months ago
I think we should allocate a large effort for system testing during the first three iterations.
upvoted 0 times
...