Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ISTQB Exam ATM Topic 2 Question 55 Discussion

Actual exam question for ISTQB's ATM exam
Question #: 55
Topic #: 2
[All ATM Questions]

Assume you have some data related to confirmation testing during system testing of a past project.

In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.

You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 personhours.

Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?

K3 2 credits

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Dong
21 days ago
Three times? Jeez, someone must have really messed up on that project. I bet the project manager was pulling their hair out during the system testing phase. At least they're learning from their mistakes, right?
upvoted 0 times
...
Jeannine
24 days ago
Ah, the old 'costs of detection' trick. Nice try, but I'm not falling for that one. 340 person-hours on confirmatory testing, and that's an internal failure cost. Gotta love these tricky questions!
upvoted 0 times
Alba
1 days ago
B) 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
upvoted 0 times
...
...
Fairy
1 months ago
Hold on, I'm trying to figure this out. If 340 person-hours were spent on confirmatory testing, and each failed test costs 3 person-hours on average, then that would make sense. But I'm not sure if it's external or internal failure. I better double-check my notes.
upvoted 0 times
...
Glory
1 months ago
Okay, let's break this down. 240 bugs were opened once, 80 twice, and 10 three times. That's a total of 340 person-hours spent on confirmatory testing, and this cost belongs to the costs of internal failure. Good thing I didn't skip that part of the study guide!
upvoted 0 times
Sherrell
3 days ago
B) 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of external failure
upvoted 0 times
...
Gail
15 days ago
A) 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
upvoted 0 times
...
...
Claudio
1 months ago
Hmm, let's see. The question is asking about the costs of confirmatory testing during system testing. Based on the information provided, I think option C is the correct answer.
upvoted 0 times
...
Sheldon
2 months ago
But if 300 person-hours have been spent on the project due to failed confirmation tests, it should belong to internal failure costs.
upvoted 0 times
...
Lawanda
2 months ago
I disagree, I believe the answer is C.
upvoted 0 times
...
Sheldon
2 months ago
I think the correct answer is A.
upvoted 0 times
...

Save Cancel