Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ISTQB Exam ATM Topic 2 Question 52 Discussion

Actual exam question for ISTQB's ATM exam
Question #: 52
Topic #: 2
[All ATM Questions]

Assume that you are the Test Manager for a small banking application development project. You have decided to adopt a risk-based testing strategy and 5 product risks (R1, R2, R3, R4, and R5) have been identified during the quality risk analysis. The following table shows the risk level associated to these product risks (higher numbers mean higher risk):

55 test cases have been designed and implemented to cover all these 5 product risks. The coverage is described in a traceability matrix.

This is the test execution status table, after the after the first week of test execution:

About 56% of the planned test cases have been successfully executed.

Assume that no additional product risks have been identified during the first week of test execution.

Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution? K3 2 credits

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Ruthann
4 days ago
I think option D is the correct answer. The test execution table doesn't provide enough information about the risk level of the remaining defects and unexecuted test cases.
upvoted 0 times
...
Frankie
7 days ago
But what about the test cases that have already passed? Shouldn't they reduce the risk level for those specific risks?
upvoted 0 times
...
Lyla
10 days ago
I agree with you, Harley. We need to wait until all test cases have been executed to determine the residual risk.
upvoted 0 times
...
Harley
15 days ago
I think the residual risk level can't be determined yet.
upvoted 0 times
...

Save Cancel