Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 11 Question 110 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 110
Topic #: 11
[All PPM-001 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Selma
3 days ago
C seems like the correct answer to me. Contingency reserves can be released for redeployment, which is a logical consequence of fast tracking.
upvoted 0 times
...
Mari
5 days ago
I think the correct answer is A. Fast tracking increases the risk of achieving the shortened project time. That's just common sense, right?
upvoted 0 times
...
Sherrell
5 days ago
I think the answer is A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...

Save Cancel