Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 11 Question 110 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 110
Topic #: 11
[All PPM-001 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Farrah
15 days ago
I don't know about you, but I'm just hoping I don't have to fast track my way out of a job after this exam. Gotta love the project management life, am I right?
upvoted 0 times
...
Serita
16 days ago
I'm going to have to go with B. The critical path will have positive total float. Sounds counterintuitive, but hey, that's project management for you!
upvoted 0 times
...
Donette
19 days ago
This is a tricky one, but I'm going with D. Duration buffers are added to maintain a focus on planned activity durations, which is a smart move when fast tracking.
upvoted 0 times
...
Sherrell
1 months ago
Hmm, that makes sense too. Fast tracking can lead to risks, but it can also free up resources for other areas of the project.
upvoted 0 times
...
Myra
1 months ago
I disagree, I believe the answer is C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Selma
2 months ago
C seems like the correct answer to me. Contingency reserves can be released for redeployment, which is a logical consequence of fast tracking.
upvoted 0 times
Danilo
13 days ago
C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Carole
1 months ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Mari
2 months ago
I think the correct answer is A. Fast tracking increases the risk of achieving the shortened project time. That's just common sense, right?
upvoted 0 times
...
Sherrell
2 months ago
I think the answer is A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...

Save Cancel