Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 11 Question 110 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 110
Topic #: 11
[All PPM-001 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Farrah
2 months ago
I don't know about you, but I'm just hoping I don't have to fast track my way out of a job after this exam. Gotta love the project management life, am I right?
upvoted 0 times
...
Serita
2 months ago
I'm going to have to go with B. The critical path will have positive total float. Sounds counterintuitive, but hey, that's project management for you!
upvoted 0 times
Gladys
1 months ago
I see your point, but I still think B) The critical path will have positive total float.
upvoted 0 times
...
Ciara
1 months ago
Actually, I'm leaning towards D) Duration buffers are added to maintain a focus on planned activity durations.
upvoted 0 times
...
Kate
2 months ago
I disagree, I believe C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Corinne
2 months ago
I think A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Donette
2 months ago
This is a tricky one, but I'm going with D. Duration buffers are added to maintain a focus on planned activity durations, which is a smart move when fast tracking.
upvoted 0 times
Gayla
27 days ago
C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Lai
1 months ago
B) The critical path will have positive total float.
upvoted 0 times
...
Brandon
2 months ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Sherrell
3 months ago
Hmm, that makes sense too. Fast tracking can lead to risks, but it can also free up resources for other areas of the project.
upvoted 0 times
...
Myra
3 months ago
I disagree, I believe the answer is C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Selma
3 months ago
C seems like the correct answer to me. Contingency reserves can be released for redeployment, which is a logical consequence of fast tracking.
upvoted 0 times
Danilo
2 months ago
C) Contingency reserves are released for redeployment by the project manager.
upvoted 0 times
...
Carole
3 months ago
A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...
...
Mari
3 months ago
I think the correct answer is A. Fast tracking increases the risk of achieving the shortened project time. That's just common sense, right?
upvoted 0 times
...
Sherrell
3 months ago
I think the answer is A) The risk of achieving the shortened project time is increased.
upvoted 0 times
...

Save Cancel