Exin Exam ASF Topic 6 Question 28 Discussion

Actual exam question for Exin's EXIN Agile Scrum Foundation exam
Question #: 28
Topic #: 6
[All EXIN Agile Scrum Foundation Questions]

Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?

Show Suggested Answer Hide Answer
Suggested Answer: A