From which sport is the term "Scrum" and much of the terminology derived?
During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.
The Lead Architect estimates two days.
The Scrum Master estimates eight days.
The team member working on it estimates seven days.
What value (in days) should be used for planning?
Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?
A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.
Who may best prepare this report?
Brandon
21 days agoFelton
1 months agoAlisha
1 months agoJesusita
2 months agoValentine
3 months agoDion
4 months agoKimberely
4 months agoYuki
4 months agoDelbert
5 months agoLaura
5 months agoAnnita
5 months agoGail
6 months agoBea
6 months agoMendy
6 months agoSamira
6 months agoGeorgene
7 months agoTammara
7 months agoCeleste
7 months agoTenesha
7 months agoJillian
8 months agoGayla
8 months agoRebbeca
8 months agoCecil
8 months agoCarma
8 months agoRuthann
9 months agoNilsa
9 months agoAmber
9 months agoAlton
9 months agoHerminia
9 months agoLorrie
10 months agoSage
10 months agoDella
10 months agoWillodean
10 months agoErasmo
11 months agoPhuong
11 months agoDick
1 years agoCarmen
1 years agoLeatha
1 years ago