Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 3 Question 7 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 7
Topic #: 3
[All PK0-005 Questions]

A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Kristel
22 hours ago
D) Record the issue and proceed with the implementation. The project is already 70% complete, and rolling back could create more issues. Plus, the sponsor didn't specify that the downtime had to be exactly 3 hours - just 'not exceed' that timeframe. Why not see if we can finish in the remaining 30 minutes?
upvoted 0 times
...
Renato
3 days ago
I think notifying customers about the delay would be the best option to manage expectations.
upvoted 0 times
...
Donette
4 days ago
We should start executing the rollback plan to minimize the impact.
upvoted 0 times
...
Louvenia
5 days ago
C) Begin executing the rollback plan. The project sponsor clearly stated the downtime should not exceed 3 hours, and with the validation process only 70% complete after 2.5 hours, it's clear the deadline will be missed. Proceeding with the implementation at this point would be irresponsible.
upvoted 0 times
...
Kami
6 days ago
We're in trouble, the downtime is taking longer than expected.
upvoted 0 times
...
Sherman
8 days ago
I agree with Mari, communication is key in situations like this. Let's go with option A.
upvoted 0 times
...
Mari
14 days ago
I think we should notify the customers about the delay and manage their expectations.
upvoted 0 times
...
Jeanice
18 days ago
We're in trouble, the validation is only 70% complete and we're almost out of time.
upvoted 0 times
...

Save Cancel