Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS TM12 Exam - Topic 5 Question 122 Discussion

Actual exam question for BCS's TM12 exam
Question #: 122
Topic #: 5
[All TM12 Questions]

Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:

- for each 10000 LOC (lines of code), 200 defects

- for each person-month of development team effort, 49 defects

You want to use this information to perform estimation for a new project.

The project manager tells you that he/she has estimated 20000 new LOC for this new project.

Four developers work for four months on this project before system testing.

During system testing, 797 defects are discovered.

Assume that the system test of this new project is using the same amount of work as spent in the past projects.

Based on this information only, which of the following statement is certainly true about this project?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Suzi
1 day ago
I think the defects found are pretty much in line with the effort.
upvoted 0 times
...
Mozell
6 days ago
The average is 200 defects per 10k LOC.
upvoted 0 times
...
Nada
12 days ago
I’m leaning towards option D because if they found more defects than expected, it suggests a higher defect density, but I’m not completely confident about the LOC delivered.
upvoted 0 times
...
Markus
17 days ago
I feel like I’ve seen a question like this before, and I think we can’t definitively say anything about the defect density without more context on the past projects.
upvoted 0 times
...
Pok
22 days ago
I think option B might be true because the number of defects usually correlates with the effort, but I'm not entirely sure how to prove it with just this data.
upvoted 0 times
...
Sueann
27 days ago
I remember that defect density is calculated based on LOC, so if we have 20000 LOC, we should expect around 400 defects, not 797.
upvoted 0 times
...

Save Cancel