Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam TM12 Topic 3 Question 17 Discussion

Actual exam question for BCS's TM12 exam
Question #: 17
Topic #: 3
[All TM12 Questions]

Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:

- for each 10000 LOC (lines of code), 200 defects

- for each person-month of development team effort, 49 defects

You want to use this information to perform estimation for a new project.

The project manager tells you that he/she has estimated 20000 new LOC for this new project.

Four developers work for four months on this project before system testing.

During system testing, 797 defects are discovered.

Assume that the system test of this new project is using the same amount of work as spent in the past projects.

Based on this information only, which of the following statement is certainly true about this project?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel