The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: ''C'' (critical defect) and ''NC'' (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
Number of correct responses: 1
A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase.
Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas.
Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?
Number of correct responses: 1
After the presentation, you are asked to explain the chart.
Assume you have applied a full risk-based testing strategy.

Which of the following answers would you expect to best describe the pie chart?
Number of correct responses: 1
Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company. Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.
Which of the following tools would you expect to be the most useful at performing this evaluation?
Number of correct responses: 1
You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system.
During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).
Which of the following risk analysis techniques are you working with?
Number of correct responses: 1
George Lewis
8 days agoTimothy Rogers
28 days agoDennis Wilson
1 month agoOlivia Flores
2 months agoJoshua Thompson
2 months agoCarol Adams
1 month agoBrenda Baker
1 month agoEdward Rivera
2 months agoAndrew Thomas
1 month agoJoanna
2 months agoGerman
3 months agoJeanice
3 months agoShawana
3 months agoYuette
3 months agoArthur
4 months agoKrissy
4 months agoAlyssa
4 months agoRebecka
4 months agoApolonia
5 months agoLuis
5 months agoOrville
5 months agoBilly
5 months agoGarry
6 months agoReyes
6 months agoDeandrea
6 months agoCorrinne
6 months agoMargarita
7 months agoHui
7 months agoElliott
7 months agoAzzie
7 months agoRasheeda
8 months agoPhil
8 months agoLonny
8 months agoJaleesa
8 months agoAdelaide
9 months agoLouis
9 months agoDominque
9 months agoIluminada
9 months agoAshley
1 year agoIdella
1 year agoLoreta
1 year agoErinn
1 year agoLisbeth
1 year agoLatia
1 year agoRusty
1 year agoMelina
1 year agoDetra
2 years agoGlory
2 years agoTresa
2 years agoLai
2 years agoChau
2 years agoSage
2 years agoEstrella
2 years agoVernice
2 years agoMarnie
2 years agoQuentin
2 years agoAn
2 years agoOneida
2 years agoAntonio
2 years agoLura
2 years agoRuthann
2 years agoBenedict
2 years agoLatricia
2 years agoJutta
2 years agoPamella
2 years agoPhung
2 years agoShawna
2 years ago