Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS TM12 Exam Questions

Exam Name: ISTQB-BCS Certified Tester Advanced Level- Test Manager
Exam Code: TM12
Related Certification(s): BCS Test Manager Certification
Certification Provider: BCS
Actual Exam Duration: 180 Minutes
Number of TM12 practice questions in our database: 65 (updated: Oct. 01, 2024)
Expected TM12 Exam Topics, as suggested by BCS :
  • Topic 1: Managing Invalid and Duplicate Defect Reports/ Evaluating Exit Criteria and Reporting
  • Topic 2: Test Prioritization and Effort Allocation in the Test Process/ Test Planning, Monitoring and Control
  • Topic 3: Improving the Testing Process with TMMI, TPI Next, CTP, STEP/ Understanding Testing Stakeholders
  • Topic 4: Assessing Process Capability with Defect Report Information/ Managing Non-Functional Testing
  • Topic 5: The Defect Lifecycle and the Software Development Lifecycle/ Alignment of Test Activities and Other Lifecycle Activities
  • Topic 6: Risk-Based Testing and Other Approaches for Test Prioritization and Effort Allocation/ Managing the Application of Industry Standards
  • Topic 7: Additional Software Development Lifecycle Activities Work Products/ Introduction to Process Improvement
  • Topic 8: Distributed, Outsourced, and INsourced Testing/ Defining and Using Test Metrics
  • Topic 9: Management Reviews and Audits/ Managing Format Reviews/ Managing Experience-Based Testing
Disscuss BCS TM12 Topics, Questions or Ask Anything Related

Antonio

4 hours ago
Skills and Training questions appeared. Know how to assess team skills and create effective training plans for testers.
upvoted 0 times
...

Lura

2 days ago
Passing the BCS ISTQB-BCS Certified Tester Advanced Level- Test Manager exam was a significant achievement for me, thanks to the practice questions from Pass4Success. There was a tricky question about Test Management that asked how to allocate resources effectively during the test execution phase. I had to think hard about the best approach, but I got through it.
upvoted 0 times
...

Ruthann

16 days ago
The exam tested knowledge on Test Closure activities. Understand what deliverables and activities are part of the test closure phase.
upvoted 0 times
...

Benedict

20 days ago
I recently passed the BCS ISTQB-BCS Certified Tester Advanced Level- Test Manager exam, and I must say, the Pass4Success practice questions were a great help. One question that stumped me was about the different phases in the Testing Process. It asked to identify the correct sequence of activities from test planning to test closure. I wasn't entirely sure of the order, but I managed to pass the exam.
upvoted 0 times
...

Latricia

27 days ago
Just passed the ISTQB-BCS Test Manager exam! Thanks Pass4Success for the spot-on practice questions.
upvoted 0 times
...

Jutta

1 months ago
Passing the BCS ISTQB-BCS Certified Tester Advanced Level- Test Manager exam was a great achievement for me, and I owe a big thanks to Pass4Success for their helpful practice questions. The topics of managing invalid and duplicate defect reports, as well as evaluating exit criteria and reporting, were key for the exam. One question that tested my knowledge was related to managing invalid and duplicate defect reports, where I had to determine the best approach for handling duplicate defects in a testing project. Despite my initial confusion, I managed to pass the exam successfully.
upvoted 0 times
...

Pamella

2 months ago
My exam experience for the BCS ISTQB-BCS Certified Tester Advanced Level- Test Manager exam was successful, thanks to the practice questions provided by Pass4Success. The topics of test prioritization and effort allocation in the test process, as well as test planning, monitoring, and control were crucial for the exam. One question that challenged me was related to test prioritization and effort allocation, where I had to decide on the most efficient way to allocate resources for testing different features. Despite my uncertainty, I was able to pass the exam.
upvoted 0 times
...

Phung

3 months ago
Just passed the ISTQB-BCS Test Manager exam! The Risk Management section was crucial. Expect questions on risk identification and mitigation strategies. Focus on understanding how to prioritize risks and their impact on test planning. Thanks to Pass4Success for the spot-on practice questions that helped me prepare efficiently!
upvoted 0 times
...

Shawna

3 months ago
I recently passed the BCS ISTQB-BCS Certified Tester Advanced Level- Test Manager exam with the help of Pass4Success practice questions. The exam covered topics such as managing invalid and duplicate defect reports, evaluating exit criteria and reporting. One question that stood out to me was related to evaluating exit criteria and reporting, where I had to determine the appropriate criteria for determining when to stop testing. Despite being unsure of the answer, I managed to pass the exam.
upvoted 0 times
...

Free BCS TM12 Exam Actual Questions

Note: Premium Questions for TM12 were last updated On Oct. 01, 2024 (see below)

Question #1

Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:

- for each 10000 LOC (lines of code), 200 defects

- for each person-month of development team effort, 49 defects

You want to use this information to perform estimation for a new project.

The project manager tells you that he/she has estimated 20000 new LOC for this new project.

Four developers work for four months on this project before system testing.

During system testing, 797 defects are discovered.

Assume that the system test of this new project is using the same amount of work as spent in the past projects.

Based on this information only, which of the following statement is certainly true about this project?

Number of correct responses: 1

Reveal Solution Hide Solution
Correct Answer: B

Question #2

You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:

Availability of re-usable test systems and documentation from previous, similar projects

Unexpected timing of components arrival

Stability of the integration test team (no turnover)

Many and geographically distributed sub-teams

Which of the following statements is true?

Number of correct responses: 1

Reveal Solution Hide Solution
Correct Answer: C

Question #3

During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a ''new'' state, indicating it needs to be investigated.

Which THREE of the following information items can't yet be present in the incident report?

Number of correct responses: 3

(2 credits out of 3 credits correct, 1 credit point)

Reveal Solution Hide Solution
Correct Answer: A, C, D

Question #4

Which of the following information would you expect to be the most useful to perform a defect clustering analysis?

Number of correct responses: 1

Reveal Solution Hide Solution
Correct Answer: B

Question #5

Consider the following statements describing the importance of improving the test process:

Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process

Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system

Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years

Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi

Which of the following answers is correct?

Number of correct responses: 1

Reveal Solution Hide Solution
Correct Answer: B


Unlock Premium TM12 Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel