Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 9 Question 79 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 79
Topic #: 9
[All ISEB-PM1 Questions]

What is the minimum a project schedule must include?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Oliva
6 days ago
I also believe that variance analysis is important to monitor and control project schedule performance.
upvoted 0 times
...
Pearlene
9 days ago
I agree with Desmond. Having planned start and finish dates for each activity is essential for tracking progress and meeting deadlines.
upvoted 0 times
...
Desmond
12 days ago
I think the minimum a project schedule must include is a planned start date and a planned finish date for each schedule activity.
upvoted 0 times
...

Save Cancel