BCS ISEB-PM1 Exam - Topic 11 Question 38 Discussion
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
A) The risk of achieving the shortened project time is increased.
B) The critical path will have positive total float.
C) Contingency reserves are released for redeployment by the project manager.
D) Duration buffers are added to maintain a focus on planned activity durations.
Clay
10 months agoOliva
10 months agoClarinda
10 months agoElza
10 months agoAlbina
10 months agoJarvis
11 months agoLisha
11 months agoAugustine
11 months agoLorrie
11 months agoLeonida
11 months agoAnisha
11 months ago