Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS ISEB-PM1 Exam - Topic 11 Question 38 Discussion

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
A) The risk of achieving the shortened project time is increased.
B) The critical path will have positive total float.
C) Contingency reserves are released for redeployment by the project manager.
D) Duration buffers are added to maintain a focus on planned activity durations.

BCS ISEB-PM1 Exam - Topic 11 Question 38 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 38
Topic #: 11
[All ISEB-PM1 Questions]

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Clay
8 months ago
Duration buffers? Sounds counterproductive to me!
upvoted 0 times
...
Oliva
8 months ago
Positive float on the critical path? Not likely!
upvoted 0 times
...
Clarinda
9 months ago
Wait, can we really release contingency reserves like that?
upvoted 0 times
...
Elza
9 months ago
I agree, the timeline gets tighter.
upvoted 0 times
...
Albina
9 months ago
Fast tracking definitely increases risk!
upvoted 0 times
...
Jarvis
9 months ago
I feel like duration buffers are more about managing delays rather than fast tracking. This question is tricky; I might need to review the definitions again.
upvoted 0 times
...
Lisha
9 months ago
Contingency reserves being released sounds familiar, but I thought that was more related to risk management than fast tracking. I’m leaning towards A as well.
upvoted 0 times
...
Augustine
9 months ago
I'm not entirely sure, but I think fast tracking could affect the critical path. I recall a practice question where it mentioned total float, but I can't remember the details.
upvoted 0 times
...
Lorrie
9 months ago
I remember studying that fast tracking can increase risks, especially if tasks are done in parallel. So, I think A might be correct.
upvoted 0 times
...
Leonida
9 months ago
I've seen questions like this before, but I'm still a bit unsure about the specifics of VRRP-A and how the VRID priority scheme affects the active/standby roles. I'll need to review my notes on this topic.
upvoted 0 times
...
Anisha
9 months ago
Okay, I've got it. The key is that the question is asking about ways a company can increase its ROI. Reducing expenses and increasing investment are both ways to do that, so A is the correct answer.
upvoted 0 times
...

Save Cancel