Your team switched to using story points for estimation in the last 2months and their sprints are 2weeks long.

Which chart can definitely help you determine the average effort that the team can deliver during each sprint?

Show Suggested Answer Hide Answer
Suggested Answer: A

The Velocity Chart shows the amount of story points completed in each sprint, allowing you to determine the average effort the team can deliver. It's specifically designed to track estimation units like story points across completed sprints.