The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
To lead the Solution Development Team effectively during the first Structured Timebox, the Project Manager should:
C . Attend the Daily Stand-up and discuss any problems at the end.
Attending the Daily Stand-up meetings allows the Project Manager to stay informed about the team's progress, challenges, and any blockers they might be facing. It offers an opportunity for the Project Manager to provide support, guidance, and decision-making where necessary, without disrupting the team's autonomy and self-organization. This approach encourages open communication, quick resolution of issues, and maintains the Agile principle of collaboration and continuous improvement. Discussing problems at the end of the meeting ensures that any issues are addressed promptly, keeping the Timebox on track.
Christiane
10 months agoAlfred
11 months agoEugene
9 months agoRolf
9 months agoFrankie
9 months agoTelma
10 months agoMaryann
10 months agoMelynda
10 months agoFelicidad
11 months agoPeter
11 months agoBrynn
10 months agoIesha
10 months agoPenney
10 months agoGilma
10 months agoRhea
10 months agoRueben
11 months agoWillard
11 months agoSol
11 months agoLanie
11 months agoFelix
11 months agoClaudia
12 months agoFannie
12 months ago