The Project management application supports two types of external dependencies. What are they?
Choose 2 answers
The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in theProduct Documentationfor ServiceNow.
Becky
3 months agoHerman
3 months agoLindy
3 months agoJacquelyne
3 months agoArt
3 months agoJaclyn
4 months agoArminda
4 months agoJeniffer
4 months agoAngelyn
4 months agoMarshall
5 months agoTijuana
5 months agoMargurite
5 months agoTamra
5 months agoRia
5 months agoBernadine
9 months agoJamey
7 months agoDiane
8 months agoPauline
8 months agoNina
8 months agoFrancine
9 months agoJesus
9 months agoAmos
9 months agoMonte
10 months agoJuan
9 months agoSheridan
9 months agoDarrin
9 months agoErinn
10 months agoAmber
10 months agoHubert
10 months agoAlise
9 months agoSantos
9 months agoMa
9 months agoCarolann
10 months agoMatthew
9 months agoLemuel
9 months agoRenato
9 months agoCiara
10 months ago