Question #: 1
Topic #: 1
[All Certified Implementation Specialist - Strategic Portfolio Management Questions]

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Show Suggested Answer Hide Answer
Suggested Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.