MultipleChoice
You manage a product development organization. One of your employees, a subject matter expert and a stakeholder for a product being developed, expresses that he feels that a newly-formed and relatively inexperienced Scrum Team lacks critical skills they will need to be successful. To fill this gap, he recommends replacing some members of the Scrum Team with new members who have better skills in the areas of concern. Based on these conversations, what do you do? (choose the best answer)
OptionsMultipleChoice
Who is responsible for managing the progress of work during a Sprint? (choose the best answer)
OptionsMultipleChoice
You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)
OptionsMultipleChoice
You manage a development organization. The Scrum Master of one of the Scrum Teams you are responsible for requests that you only communicate with the team through her. What do you do? (choose the best answer)
Options