Question #: 14
Topic #: 5
[All C_TS414_2023 Questions]

You post a goods receipt for a purchasing document and inspection type 01 is active in the material master. The supplier has not provided the mandatory quality certificate.Which of the following process steps Is possible?Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

0/2000 characters
Trina
3 months ago
Isn't it risky to proceed without that quality certificate?
upvoted 0 times
...
Rachael
3 months ago
Agree with Susana, defects can be recorded.
upvoted 0 times
...
Earlean
3 months ago
Wait, can you really confirm the certificate after the decision? Seems off.
upvoted 0 times
...
Susana
4 months ago
I think recording defects is also possible here.
upvoted 0 times
...
Regenia
4 months ago
You can definitely post the usage decision.
upvoted 0 times
...
Selene
4 months ago
I believe recording defects is definitely possible, but I’m not confident about the confirmation of the certificate.
upvoted 0 times
...
Whitley
4 months ago
I’m a bit confused; can we really post a usage decision without the quality certificate? That seems risky.
upvoted 0 times
...
Ramonita
4 months ago
I remember practicing a similar question, and I feel like recording inspection results might be an option here.
upvoted 0 times
...
Izetta
5 months ago
I think we can confirm the certificate receipt after making a usage decision, but I'm not entirely sure about the other options.
upvoted 0 times
...
Brendan
5 months ago
Based on the information provided, I believe the two correct answers are recording the inspection results and posting the usage decision. The certificate issue complicates things, but those seem like the logical next moves.
upvoted 0 times
...
Lisbeth
5 months ago
Hmm, I'm a bit unsure about this one. I'll need to review the material master and purchasing document details to determine the appropriate next steps.
upvoted 0 times
...
Fletcher
5 months ago
I'm pretty confident I know the correct answers here. The supplier's lack of a quality certificate is an issue, but there are still a couple options available.
upvoted 0 times
...
Nida
5 months ago
Okay, let me think this through step-by-step. The supplier didn't provide the mandatory quality certificate, and inspection type 01 is active. I'll need to carefully consider the possible process steps.
upvoted 0 times
...
Cathrine
5 months ago
This question seems straightforward, but I want to make sure I understand the key details before answering.
upvoted 0 times
...
Antione
1 year ago
B and C are my picks. Gotta love those inspection results, they're the spice of life!
upvoted 0 times
Dorathy
1 year ago
D) Recording of defects
upvoted 0 times
...
Dortha
1 year ago
C) Posting of the usage decision
upvoted 0 times
...
Ashlyn
1 year ago
B) iS Recording of inspection results
upvoted 0 times
...
Ira
1 year ago
A) Confirmation of certificate receipt after usage decision
upvoted 0 times
...
...
Eleonore
1 year ago
Haha, I bet the supplier forgot the certificate because they were busy playing a game of 'hide-and-seek' with the quality team.
upvoted 0 times
Teddy
1 year ago
B) iS Recording of inspection results
upvoted 0 times
...
Detra
1 year ago
A) Confirmation of certificate receipt after usage decision
upvoted 0 times
...
...
Elly
1 year ago
D is also a valid option. Recording any defects found during the inspection process is crucial.
upvoted 0 times
Brett
1 year ago
B) iS Recording of inspection results
upvoted 0 times
...
Myrtie
1 year ago
D) Recording of defects
upvoted 0 times
...
Karan
1 year ago
A) Confirmation of certificate receipt after usage decision
upvoted 0 times
...
...
Clement
1 year ago
I think A and C are the correct answers. Posting the usage decision seems like a logical step after confirming the certificate receipt.
upvoted 0 times
Darci
1 year ago
No, recording of defects is not necessary if the supplier has not provided the mandatory quality certificate.
upvoted 0 times
...
Graham
1 year ago
What about recording of defects? Do you think that is necessary in this case?
upvoted 0 times
...
Aleta
1 year ago
Yes, you are correct. Posting the usage decision is necessary after confirming the certificate receipt.
upvoted 0 times
...
Hermila
1 year ago
I think A and C are the correct answers.
upvoted 0 times
...
Eva
1 year ago
Yes, those steps are necessary for handling the situation.
upvoted 0 times
...
Tasia
1 year ago
I agree, posting the usage decision makes sense after confirming the certificate receipt.
upvoted 0 times
...
Chandra
1 year ago
I think A and C are the correct answers.
upvoted 0 times
...
...
Candida
1 year ago
I'm not sure about the options. Can someone explain why recording of defects is not a possible process step in this scenario?
upvoted 0 times
...
Casie
1 year ago
I agree with Donte. Confirmation of certificate receipt after usage decision and posting of the usage decision seem like the correct options.
upvoted 0 times
...
Donte
1 year ago
I think the possible process steps are A and C.
upvoted 0 times
...