SAP C_TS412_2021 Exam - Topic 5 Question 15 Discussion
Project StructuresWhich the following statement regarding networks are correct?.Note : there are 3 correct answers for this question.
B) You can assign more than one activity element to a network activity. and C) Capacity requirements of a network activity are reduced when the activity is confirmed. and E) You can assign the same work center to more than one activity on the same network.
A) If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
D) During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
Eve
6 months agoYong
7 months agoPearline
7 months agoShanice
7 months agoHershel
7 months agoTeddy
7 months agoHeike
8 months agoOretha
8 months agoChaya
8 months agoDalene
8 months agoNana
8 months agoNina
8 months agoKindra
8 months agoJoseph
8 months agoHillary
8 months agoSherill
8 months agoWilda
8 months agoCecilia
8 months ago