SAP Exam C_TS412_2021 Topic 4 Question 12 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 12
Topic #: 4
[All C_TS412_2021 Questions]

Which object is used to allocate the costs from a claim to the project structure?

Show Suggested Answer Hide Answer
Suggested Answer: A, D

The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are:

Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator ''Requirements immediately'' in customizing for your project profile.

When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator ''Requirements on release'' in customizing for your network type or activity type. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002


Contribute your Thoughts:

Tamra
2 months ago
I heard the correct answer is a magic 8-ball. Shake it and see what it says!
upvoted 0 times
Solange
6 days ago
D) WBS element
upvoted 0 times
...
Asuncion
7 days ago
C) Claim
upvoted 0 times
...
Adolph
8 days ago
B) Internal order
upvoted 0 times
...
Mabel
23 days ago
A) Network activity
upvoted 0 times
...
...
Olga
2 months ago
Network activity? What is this, a detective novel? Clearly, the WBS element is the way to go.
upvoted 0 times
...
Justine
2 months ago
Ah, the age-old question of where to put the claim costs. I'm feeling lucky, let's go with C, Claim!
upvoted 0 times
...
Penney
2 months ago
Internal order? Really? That's for managing internal operations, not for claims. I'm going with D, WBS element.
upvoted 0 times
Dyan
2 days ago
I think it might be Network activity, as it tracks the progress of the project.
upvoted 0 times
...
Casie
3 days ago
I agree, WBS element is used to allocate costs to the project structure.
upvoted 0 times
...
Verlene
5 days ago
Yeah, I'm changing my answer to D) WBS element as well.
upvoted 0 times
...
Marylyn
6 days ago
I agree, I'll go with D) WBS element too.
upvoted 0 times
...
Janessa
17 days ago
I'm not sure, but I think it might be D) WBS element.
upvoted 0 times
...
Aimee
2 months ago
I think it's A) Network activity.
upvoted 0 times
...
...
Mabel
2 months ago
I think the WBS element is the correct choice here. That's where we allocate the costs from a claim, right?
upvoted 0 times
...
Vesta
2 months ago
I'm not sure, but I think it could also be A) Network activity, as it is used to track project tasks.
upvoted 0 times
...
Eden
2 months ago
I agree with Glory, because the WBS element is used to allocate costs to the project structure.
upvoted 0 times
...
Glory
2 months ago
I think the answer is D) WBS element.
upvoted 0 times
...
Romana
2 months ago
I'm not sure, but I think it might be A) Network activity. Can someone explain why it's D) WBS element?
upvoted 0 times
...
Alaine
3 months ago
I agree with Yong, because the WBS element is used to allocate costs in project management.
upvoted 0 times
...
Yong
3 months ago
I think the answer is D) WBS element.