Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set
of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
Micaela
1 years agoGlennis
1 years agoIrving
11 months agoCecilia
12 months agoLorrie
12 months agoAlba
1 years agoEttie
1 years agoJesusa
1 years agoElenore
1 years agoLuke
12 months agoStacey
1 years agoMicaela
1 years agoRikki
1 years agoLizbeth
1 years agoStefania
1 years agoLauryn
1 years agoRuth
1 years agoMartina
1 years agoFranchesca
1 years ago