Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set
of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
Kendra
10 months agoCrista
10 months agoNichelle
10 months agoRicki
11 months agoKing
11 months agoTiffiny
11 months agoDaron
11 months agoAlease
11 months agoBettyann
11 months agoTammara
12 months agoAudria
12 months agoDaren
12 months agoEloisa
12 months agoMargurite
12 months agoAudry
12 months agoEmogene
12 months agoMicaela
2 years agoGlennis
2 years agoIrving
2 years agoCecilia
2 years agoLorrie
2 years agoAlba
2 years agoEttie
2 years agoJesusa
2 years agoElenore
2 years agoLuke
2 years agoStacey
2 years agoMicaela
2 years agoRikki
2 years agoLizbeth
2 years agoStefania
2 years agoLauryn
2 years agoRuth
2 years agoMartina
2 years agoFranchesca
2 years ago