Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set
of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
Micaela
11 months agoGlennis
11 months agoIrving
10 months agoCecilia
10 months agoLorrie
10 months agoAlba
11 months agoEttie
11 months agoJesusa
11 months agoElenore
11 months agoLuke
10 months agoStacey
11 months agoMicaela
11 months agoRikki
11 months agoLizbeth
11 months agoStefania
11 months agoLauryn
11 months agoRuth
12 months agoMartina
12 months agoFranchesca
1 years ago