Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, E

In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:

Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.

Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


Contribute your Thoughts:

0/2000 characters
Kendra
3 months ago
Basic dates are definitely not used for scheduling networks.
upvoted 0 times
...
Crista
3 months ago
Wait, are there really only two correct answers?
upvoted 0 times
...
Nichelle
3 months ago
I thought Fundamental dates were also an option?
upvoted 0 times
...
Ricki
4 months ago
Totally agree with you!
upvoted 0 times
...
King
4 months ago
Planned dates and Baseline dates are the ones!
upvoted 0 times
...
Tiffiny
4 months ago
I feel like basic dates could be relevant, but I’m leaning towards planned and baseline dates as the correct answers.
upvoted 0 times
...
Daron
4 months ago
I’m a bit confused; I thought fundamental dates were used in scheduling too, but I can't recall if they apply here.
upvoted 0 times
...
Alease
4 months ago
I remember practicing a question like this, and I think baseline dates might be the other option.
upvoted 0 times
...
Bettyann
5 months ago
I think the planned dates are definitely one of the correct answers, but I'm not sure about the second one.
upvoted 0 times
...
Tammara
5 months ago
I'm not entirely confident about this one. I'll need to review the material on project system dates again before answering.
upvoted 0 times
...
Audria
5 months ago
I've got this! Planned dates and Baseline dates are the two sets of dates that can be used for scheduling in the SAP project system network.
upvoted 0 times
...
Daren
5 months ago
Okay, let me think this through. The question is asking about scheduling for a network, so I'm guessing Planned dates and Forecast dates would be the relevant options.
upvoted 0 times
...
Eloisa
5 months ago
I'm a bit confused here. Are Fundamental dates and Basic dates the same thing? I'll need to double-check the definitions to be sure.
upvoted 0 times
...
Margurite
5 months ago
Hmm, this seems straightforward. I think the two correct answers are Planned dates and Baseline dates.
upvoted 0 times
...
Audry
5 months ago
This seems like a straightforward question about what should be included in a report on internal control matters. I'm pretty confident I can handle this.
upvoted 0 times
...
Emogene
5 months ago
Okay, let me break this down step-by-step. First, we set up the Cluster Master and configure the base app. Then we add the indexers one by one, with each one joining the cluster. I'm guessing the cluster would be ready to ingest data once all three indexers have successfully joined.
upvoted 0 times
...
Micaela
2 years ago
Yeah, those two seem like the most logical options based on the requirements of the project system.
upvoted 0 times
...
Glennis
2 years ago
Did someone say 'scheduling'? I'm on it! A) Planned dates and D) Baseline dates are the way to go. Though I'm tempted to throw in a wild card like C) Basic dates just to keep the professor on their toes.
upvoted 0 times
Irving
2 years ago
Let's stick with the safe choices of A) Planned dates and D) Baseline dates for scheduling.
upvoted 0 times
...
Cecilia
2 years ago
I think C) Basic dates could also be a good option to consider, just to cover all bases.
upvoted 0 times
...
Lorrie
2 years ago
I agree, A) Planned dates and D) Baseline dates are the best choices for scheduling.
upvoted 0 times
...
...
Alba
2 years ago
I'm not sure about Fundamental, Basic, or Forecast dates, but I think Planned and Baseline dates are commonly used for scheduling tasks.
upvoted 0 times
...
Ettie
2 years ago
I agree with Micaela, Planned dates and Baseline dates make sense for scheduling in the network.
upvoted 0 times
...
Jesusa
2 years ago
This is easy! A) Planned dates and D) Baseline dates for sure. I mean, why would they even ask about 'basic' or 'forecast' dates? That's just silly.
upvoted 0 times
...
Elenore
2 years ago
I'm going with B) Fundamental dates and E) Forecast dates. Gotta think outside the box, you know? Who needs 'planned' dates when you can have 'fundamental' ones?
upvoted 0 times
Luke
2 years ago
I agree with you, I also chose B) Fundamental dates and E) Forecast dates.
upvoted 0 times
...
Stacey
2 years ago
I think A) Planned dates and C) Basic dates are the correct options.
upvoted 0 times
...
...
Micaela
2 years ago
I think the correct answers are A) Planned dates and D) Baseline dates.
upvoted 0 times
...
Rikki
2 years ago
Hmm, I think the answer is A) Planned dates and D) Baseline dates. Those seem to be the most relevant for scheduling networks in the project system.
upvoted 0 times
Lizbeth
2 years ago
Yes, those are the dates that are commonly used for specifying planned dates of tasks in the project system.
upvoted 0 times
...
Stefania
2 years ago
I agree, A) Planned dates and D) Baseline dates are the correct options for scheduling networks.
upvoted 0 times
...
...
Lauryn
2 years ago
I don't think Fundamental dates would be used for scheduling network tasks. It seems more like Planned dates and Baseline dates would be the ones.
upvoted 0 times
...
Ruth
2 years ago
I'm not sure about Fundamental dates. Does anyone think that could be one of the correct answers?
upvoted 0 times
...
Martina
2 years ago
I agree with you, Franchesca. Planned dates and Baseline dates make the most sense for scheduling network tasks.
upvoted 0 times
...
Franchesca
2 years ago
I think the correct answers are A) Planned dates and D) Baseline dates.
upvoted 0 times
...

Save Cancel