SAP C_S4PPM_2021 Exam - Topic 3 Question 59 Discussion
Which system behavior are enabled when a create a project with multiple phase?NOTE: There are 2 correct answers to this question.
A) Determination of the start-dates of subsequent phases and D) Determination of the start- and end-dates of tasks
B) Rollup of activity cost allocations to phases
C) Rollup of resource requirements of tasks to phases