PRINCE2 Exam PRINCE2-Foundation Topic 5 Question 82 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 82
Topic #: 5
[All PRINCE2-Foundation Questions]

Which does the Executive need to ensure is in place before the project is initiated?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Fatima
7 days ago
I believe having an understanding of how the project will contribute to corporate objectives is also crucial for the Executive before initiating the project.
upvoted 0 times
...
Graham
7 days ago
I think the correct answer is option D. The Project Initiation Documentation should be complete before the project is initiated, as it lays out the scope, objectives, and other key details.
upvoted 0 times
...
Lucia
10 days ago
I agree with An. Without the Project Initiation Documentation being complete, the project may face uncertainties and delays.
upvoted 0 times
...
An
12 days ago
I think the Executive needs to ensure that the Project Initiation Documentation is complete before initiating the project.
upvoted 0 times
...