Question #: 77
Topic #: 2
[All PRINCE2-Agile-Foundation Questions]

Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Odette
3 days ago
C) Because it enables agile to be used in challenging and uncertain situations - this aligns with the core principles of Lean Startup, which is all about rapid experimentation and adaptation.
upvoted 0 times
...